Congressional Serial Set Project Charter

Contact Information

Requesting Department:

Government Information

Department Contact:

Jen Kirk

Cataloger(s):

Kurt Alan Meyer

Time

Est. Total Time:

Approximate from test run

Est. Start Date:

February 2021

Est. End Date:

TBD

Project Details

Quantity:

11,300

Equipment Needed:

None anticipated

 

1. Overview:

In an effort to address compact shelving issues, Government Information will need to catalog materials that could potentially be moved to the BARN. One collection that has been identified is the Congressional Serial Set. There are over 15,000 volumes in this set, with 11,000 volumes stored in a run under the X call number. Given the large size of the collection, Gov Info, CMS, and the Integrated Systems Librarian agreed via email in October 2020 to investigate methods for batch processing the cataloging of this collection. The group identified a strategy for cataloging by Congresses (years) that will include creating a record for each year and attaching individual items to these general records. Individual title level cataloging will not be the primary goal. The most pressing constraint is that no single record can include more than 500 item records attached.

 

2. Project Team, Roles and Responsibilities:

Team Member

Role

Responsibility

Kurt Meyer

Lead cataloger/project manager

Title Level Cataloging

Melanie Shaw

Cataloger

Batch Level Cataloging

Barbara Fleming

Cataloger

Holdings Creator

Andrea Payant

Cataloger

Batch level (backup)

Jen Kirk

Government Information head

Decision maker

Liz Woolcott

CMS unit head

Batch Level Cataloging

 

3. Costs

Item Name

Unit cost

No. of Units

Est. Total

Barcodes

$0.01

11,300

$113

Labels

$0.01

11,300

$113

Est. Total

 

 

$226

 

CMS will include barcode estimates in next order for barcodes. These funds come from the general library fund. No additional funding is required.

 

4. Timeline and Benchmarks:

Date(s)

Activity

Benchmarks/Goals

Assigned to:

Feb. 2021

Set an initial meeting with Gov Info

Outline the project timeline and process

Liz

Feb-March 19, 2021

Pre-Process Test batch 18th-33rd Congress

Barcode/record for first 250ish items

Jen

Feb-March 19, 2019

Draft process/procedures

Assign and train catalogers on project

Procedures drafted

Melanie, Kurt, Liz

By April 2, 2021

Barcode and catalog 250ish items/week

Have 1st 1,000 Items barcoded / cataloged

All Team

April 19-30, 2021

Test Phase

Team will track time, numbers of items, and errors/issues. Report on projected time to completion

All team

May - TBD

Batch level cataloging

TBD

Melanie, (additional batch loader)

May – TBD

Individual title level cataloging

TBD

Kurt

May – TBD

Holdings records created

TBD

Barb

 

 

 

 

 

5. Statistics and Tracking

Airtable will be used for tracking purposes. A base has been set up by the Government Information Librarian: Serial Set Area Shelflist (https://airtable.com/shrQO4bFmhRs5BSBq) that can be used.

Statistics (for CMS) will be recorded in the CMS Stats Airtable base and will include GovDocs-OriginalCat-Physical, Sierra-Items Added, and if needed, Sierra-Holdings Created.

6. Communication Expectations/Reporting:

Beyond the initial meeting, the team will report monthly on the progress of the project. Reports will be submitted by the Government Information and E-Resources Cataloger in the form of the monthly updates to the Cataloging Projects and Ongoing Work form: https://airtable.com/shrUK6bTlUAD732HS Additional reports will be pulled from Airtable, as needed.

 

7. Workflows/Procedures

Workflows and processes for this project will be kept in a publicly accessible Confluence page to ensure that CMS and Gov Info have access to the process. Procedures for this project are documented here: